|
PROGRESS AS AT 12th JANUARY 2012. CURRENT WORKING PARTY: Charlie
Jones - Team Leader, Jeff Jackson, Rod Wallis, Chris Tayler, John Spaul, Mike Tayler, Andrew Jones, Geoff F &
Roger Fox. WORK IN PROGRESS
LOCO
FRAME AND MOTION: 95% The frame and motion is completed. Although, due to it being
almost 20 years since the journals were checked and passed as fit, we plan to drop the driving wheels to check the journals
and bearings while the boiler is out of the frames. The locomotive and tender were reunited for the first time in 15 years
on 2nd September 2008 when they took up residence in our new shed (the ex King shed). TENDER FRAME: 100%
The tender frame and running gear are complete. BOILER:
25% We had a cold boiler inspection done by two different inspectors on 29th August 06.
Their findings were that the boiler is in very good overall condition. The boiler was lifted on 5th May. The following work
is required and in progress: - Renew all flue tubes. Tubes procured. Large tubes having bottle ends fitted
at Tyseley.
- Replace all firebox stay nuts. Done.
- Replace 800 steel stays. Done
– some need length trimming.
- Copper welding to build up a small area of the front tube plate.
- Replace
palm stays.
- Replace 40 copper stays.
- Rethread all washout plugs. Done.
- Replace
foundation ring studs. In hand.
- Weld areas around the mud hole doors where slight erosion has taken
place.
- Repair small cracks to firebox outer wrapper lower corners of back head and throat plate. Detected by NDT.
Repair scheme to be agreed.
The super-heater header was shipped to a specialist fusion welding
company for repair and machining week 3 July. A new back head plate has been made. The boiler is being needle
gunned to remove the old red oxide paint and it is being repainted in high temperature silver. 35% done. ENGINE
CLADDING: 10% - The steam pipe covers, safety valve bonnet and base and smoke box blower pipe cover are all manufactured
and trial fitted, but are now removed and stored for boiler refurb.
- The firebox elephants ears have been collected
from the SDR.
- All 8 crinoline bands are manufactured and trial fitted, but are now removed and stored for the boiler
refurb.
TENDER BRAKES: 95% The tender brake system is virtually completed and requires only final adjustment,
fitting of spacers and split pins. TENDER TANK: 75% - The tank base
plate, rear and sides are located and the joints seam welded. New tank top rear corner pieces have been manufactured and welded
in place.
- The tank skirt has been fixed all round to the base with dome head bolts instead of rivets, for ease of
future maintenance.
- All baffles are tacked in place and are being aligned then rivetted/welded as we progress forwards
towards the tank front.
- The tank front plate and coal shute are now tacked in position ready for seam welding.
- The
water filler ring and water dispersion dome are fitted to the tank top.
- The toolboxes and coal bunker door supports
are repaired and painted ready for assembly.
- The beading for the joints and edges of the tank has been removed from
the old tank, cleaned up and is being rivetted to the tank.
- The
front and rear grab rails have been remanufactured and fitted.
- Hydrant connections are fitted, one to each side just
forward of the rear axle set.
- The water gauge float mechanism is fitted.
- The water and brake columns
are now fixed to the tank front.
WATER FEEDS: 90% - The hose
couplings are fitted to the tender. The hose couplings for the loco injector water feeds are on order.
- The water
valve controls are being refurbished and fitted.
STEAM HEAT: 95%
- Manufacture and fitting of the "fixed" steam heat pipes is completed on the tender and is 95%
completed on the locomotive.
- The drip trap casting for the loco has been procured and is being machined.
- The
copper pipe for the feed to the control valve in the cab is being sourced.
- The pipes are 90% lagged on the loco and
100% on the tender.
- The flexible hoses for the steam heat on the front of the loco and rear of the tender are fitted.
INJECTORS AND CLACK VALVES: 70% - Both live steam
injectors are fitted.
- The copper and steel water feed pipes between the injectors and clack valves is completed.
(top feed pipes removed for boiler refurb)
- The injector live steam feed copper pipes are bent to approximate shape
and are trial fitted on both sides (removed for boiler refurb).
- The injector overflow valves are fitted and the overflow
pipes manufactured and fitted.
- The fixed injector water feed fixed pipes are fitted.
LOCO
BRAKING SYSTEMS: 90% - All of the brake components and large vacuum pipes are on the loco.
- Approx
90% of smaller bore pipe work is done.
- The vacuum retaining valve is fitted and all 3 of the connections to it, including
flexible hoses, are fitted. The pipe run from the vacuum retaining valve to the ejector is now made up and fitted as far as
we can. The final section needs the boiler back in the frame and the ejector mounted.
- The vacuum pump has been refurbished
and fitted.
- The pipe run to the cab controls is 95% made up.
- The Pepperpot Valve is fitted.
- We
need to procure a vacuum non-return valve. Procurement in hand.
- The loco to tender vacuum flexible
hoses are fitted.
CAB FITOUT: 70% All of
the cab components have been trial fitted and are now removed for the boiler refurb. The cab floor is part fitted. LUBRICATION
SYSTEMS: 5% The pipe fittings for the lubrication pipe work have been procured and work on fitting
the pipes is in progress. ASHPAN/DAMPER CONTROLS: 55%: - The
ashpan has been refurbished.
- The hopper door operating fulcrum is refurbished and needs only brackets making up to
fit it to the loco.
- All of the hopper and damper control rods have been cleaned up and painted ready to fit.
LIVERY:
55% - Both nameplates, 38G shed plate and smoke box number plate are fitted (38G refers to the shed code designation
of Quainton by Steam Railway some years ago). We have made a bracket for the "Cathedrals Express" headboard and
it is put on the engine for special events.
- The loco will be finished in Brunswick Green with post 56 tender BR logo.
INFRASTRUCTURE The
tracks into the shed have been re-laid with concrete in-fill so as to make the transfer of heavy equipment between both sides
of the loco easier and safer. A redundant signalling cabinet has been installed next to the boiler pad and fitted out
with 110V and 3 phase supplies to make it easier to work on the boiler.
CAN
YOU HELP? We are always in need of volunteers to assist with the restoration. You do not have to be a locomotive
engineer -although it would be great if you are - there is plenty to do for all abilities. We run working parties most Sundays
and Tuesday and Wednesday every 4 weeks ( see the schedule above) the whole year round. We always need more volunteers. If
you want to help you need to be a member of the Quainton Railway Society - for insurance purposes. Interested? then contact
Chartlie Jones on 01525 635860, or Jeff Jackson on 01278 781649 (before 20:00).
|